STRIP-OUT e DECOMMISSIONING di Immobili ed Impianti

Wednesday, 01 June 2016 00:00

IMPAR

Written by

Description of the job

      Re-roofing intervention on Azienda Agricola Fenil Ronchi's dwelling-warehouse in Verolanuova (Brescia).

    Reconstruction of the south-facing part of the roof, with building integration of a photovoltaic system.

Technical data

  • Total roofing area: 1060 m2
  • Total south-facing roof area: 696 m2
  • Power of the photovoltaic system: 82.28 kWp
  • Electrical power production: 95,000 kW/h per year
  • Amount of the contract: 660,000 €
  • Annual revenue from national energy incentives: 48,850 €
  • 20-year revenue from national energy incentives: 879,000 €

 

impar

Data

Customer: IMPAR Immobili e Partecipazioni S.r.l.

Area: Cascina Ronchi - Verolanuova (BS)

 

 

IMPAR Immobili e Partecipazioni

impar

Customer: IMPAR Immobili e Partecipazioni S.r.l.

Area: Verolanuova (BS)
 

Show tab

IN.G.RE

ingre 1

Customer: IN.G.RE.

Area: Milano
 

Show tab

 

Wednesday, 01 June 2016 00:00

INGRE

Written by

Remediation of polluted soils. Waste management plan, former-Romagnina area in Milan.

The area subject to remediation is included in the U3 intervention unit of the Integrated Intervention Plan for the Garibaldi Repubblica area and falls within the urban development programme of the new Lombardy Region's Administration. This area was intended to be transformed into a public park; the surface to be excavated and sent to an external plant was approx. 1,001 m2. The interventions carried out are the following:

  • Validation of soils from each cell to determine their EWC and a suitable disposal site;
  • Filling ground excavation;
  • Loading and removal of excavated materials, according to their contamination and validations;
  • Tests of excavation walls and bottom;
  • Backfilling with certified material.

These interventions were carried out in an urban area, where spaces available for operational and worksite needs were limited. Our company had to cope with the following limits:

  • partial space and time availability of the working areas;
  • car traffic in the areas just outside the worksite, where the operations had to be carried out;
  • need to guarantee pedestrian and car passages for inhabitants and shop workers;
  • recovery of the areas used.

All precautions needed were taken to minimise the production and the emission of pollutants, such as noise, powders, vibrations, etc., in compliance with environmental regulations and local regulations.

  • Extra operations, which had not been foreseen, were needed:
  • Tank draining and cleaning
  • EWC 160708 sludge disposal, transport included
  • EWC 160708 gas oil and washing effluent disposal
  • LSC soils disposal, including transport and incineration EWC 160708*
  • Plinth demolition
  • Ferrous material recovery
  • Assistance for war material removal

 

ingre 1

Data

Customer: IN.G.RE.

Area: Milano

Construction site: area ex Romagnina (zona Repubblica Garibaldi)

Work Termination: 2012

 

 

Wednesday, 01 June 2016 00:00

Miroglio

Written by

Description of the job

The reclamation of the former Valtanaro dyeworks which currently hosts the new Miroglio logistic centre, required asbestos-removal work on machinery, pipes and roofing. Tecnologie Industriali & Ambientali carried out the asbestos and mineral fibre removal operations, but also mechanical demolitions and re-roofing on a surface of approx. 17,000 m2.

Interventions were carried out on:
  • some dying machineries containing friable asbestos mainly in their gaskets. A static-dynamic confinement was required
  • pipes of approx. 11,000 ml coated with mineral wool
  • cement-asbestos roofing 17.000 mq.
Mechanical demolitions involved:
  • machineries, tanks, silos, brackets and pipes

 

The intervention also included the selective sorting of waste materials (mineral wool, steel, aluminium, electrical cables, etc.), iron recovery and disposal of materials in authorised landfills. The roofing reclamation was carried out on a surface of 17,000 m2. The reconstruction included:
  • steam barrier recovery
  • installation of new insulating systems
  • installation of new roofing
  • eaves waterproofing
  • installation of new pitches

Critical points

In order to respect the timing set for the reclamation of the whole complex, demolition, remediation and reconstruction works were carried out in only 6 months. This required a huge organisation and coordination work.

Amount of the contract: € 900.000

Technical data

  • Number of technical managers: 1
  • Number of project managers: 1
  • Number of worksite managers: 2
  • Number of specialised workers: 12

 

eternitmiroglio

Data

Customer: Miroglio

Construction site: former dyeing factory Valtanaro

Area: Castagnole Lanze (CN)

Work Period: 6 months

Work Termination: December 2008

 

 

 

Miroglio

eternitmiroglio

Customer: Miroglio

Area: Castagnole Lanze (CN)

Show tab

 

 

Wednesday, 01 June 2016 00:00

MUNICIPALITY OF SIENA

Written by

Description of the job

The area to be treated was the landfill in the Municipality of Siena. This contaminated area contained two main types of waste:

  • the first contained shredded waste of different types (wet waste, plastic and urban waste)
  • the second was made of dioxin-containing ashes.

Two different codes were used to classify these types of waste

  • EWC 191302, which identifies solid waste from remediated areas.
  • EWC 170504, which identifies non-dangerous soils, whose dioxin content is below the risk level

The shredded material and the dioxin-containing soil were in different areas.

Critical points

  • Time available was limited and this required careful organisation to removal and dispose of the soils so as to create a continuous flow from removal to disposal. This continuous flow made it possible to optimise the efficiency of machines and eliminate waiting times. The excavation pace produced 600/800 tons of soil per day on average, corresponding to approx. 25 trucks per day. This method made it possible to remove and dispose of all of the material in five months.

Difficulties faced

  • Due to the scope of the job a workers dormitory, changing rooms and shower rooms were set up at the work site,. An office and a workshop were also built for the extraordinary maintenance of vehicles.
    A truck wheel washing installation was set up to prevent pollutants from being taken out from the worksite as much as possible . Runoff water was also treated.

Worksite setting up

  • Within the excavation area there were several underground utilities, such as gas network and sewage network, whose position was not always clearly defined and this required great attention to prevent damages. This situation caused a slowdown of excavation phases and required the continuous excavation-disposal flow to be adapted in order to avoid waiting times

Technical data

  • Excavation volume: 43,000 m3
  • 1 work site manager
  • two 1 m3 bucket bulldozers
  • one 140 hp tracked excavator
  • six 300,000 kg trucks
  • Amount of the contract: 1,112,000 €

 

siena

Data

Customer: Municipality of Siena

Area: Siena

Construction site: intervention of environmental decontamination at the former "Mattonaia and Cerchiaia area", with landfill disposal

Work Period: 5 months

Work Termination: February 2004

 

 

Municipality of Siena

siena

Customer: Municipality of Siena

Area: Siena

Show tab

 

 

Wednesday, 01 June 2016 00:00

NUOVA PASTICCERIA

Written by

Description of the job

  • Asbestos removal and reconstruction of the building's roofing
  • Installation of a total building integrated photovoltaic system

Technical data

  • Removal of 1,145 m2 of cement-asbestos
  • Roofing reconstruction with sandwich panels
  • Installation of 424 poly-crystalline silicon photovoltaic modules
  • Power of the photovoltaic system installed: 93 kWp
  • Roof pitch 6° and 21°
  • -35° South-East orientation
  • Surface used: approx. 950 m2

 

nuova pasticceria

Data

Customer: NUOVA PASTICCERIA

Area: San Giuliano Milanese (MI)

Construction site: General direction

Work Termination: 2010

 

 

Nuova Pasticceria

nuova pasticceria

Customer: Nuova Pasticceria

Area: San Giuliano Milanese (MI)
 

Show tab

 

Page 4 of 5

OUR HISTORY

The TIA group was founded after the war and became the leading asbestos removal company in Italy in the 1990s.

Read more

CONTACT US

Address: via Salomone 73, 20138 Milano (IT)
Phone number: +39 02 50 99 40 1
E-mail address: This email address is being protected from spambots. You need JavaScript enabled to view it.

Location

Top
Con la presente informativa sul trattamento dei dati personali desideriamo informarla circa le modalità e le finalità di trattamento dei dati personali raccolti durante la navigazione sul sito web www.tia.it, in conformità a quanto previsto Regolamento generale europeo (UE) sulla protezione dei dati Personali (Regolamento UE 2016/679).