STRIP-OUT e DECOMMISSIONING di Immobili ed Impianti

Description of the job

  • Asbestos decontamination of metallic structures
  • Partial demolition and reconstruction of the false ceiling
  • Re-insulation with fire protection
  • • This was the first and the largest remediation intervention carried out in Italy on a civil building, which was kept habitable for the whole duration of the works.

Test phase

  • Between 1987 and 1989, the first decontamination was carried out on two floors, where the managers' offices were. This experience was essential to create a complex working plan for the remediation of the whole building. We can call this a pilot intervention, as we had to tackle all the main problems posed by the remediation of a working environment which is only partially empty.

Difficulties faced

  • The decontamination was carried out on one floor at a time, with filter floors above and below for refurbishment interventions only.

Critical points

  • The building hosting Ente Poste and Telecom offices kept being used for all the duration of the works. Another building was built to temporarily host the offices from the floors being decontaminated.

Innovative solutions adopted

  • This was the first intervention where a 200 m2 large prefabricated decontamination unit was used.
  • Amount of the contract: €. 3.594.540

Technical data

Area treated:

  • 17-storey building, 2,000 m2 per floor

  • N° worksite managers: 1
    N° specialised workers: 10
    N° total workers: 25

  • m2 treated: approx. 34,000
    m3 treated: 1,100 m3 of toxic-dangerous waste

 

protel

Data

Customer: Protel

Area: Roma

Construction site: Poste Italiane

Work Termination: June 1999

 

 

Description of the job

Remediation and demolition of Cet 1 installation:

  • removal of all asbestos and mineral fibres insulation systems
  • removal of fluids and residues from the installations
  • controlled demolition flush with the floor and recovery of ferrous materials
  • construction of structural reinforcements for the remaining installations

30 specialised workers worked for one year and a half for the removal of asbestos and other dangerous substances. Other teams of technicians and workers carried out the controlled demolition works in the plant and the structural reinforcements; these activities were realised discontinuously.

Technical data

Dimensions:

  • mq. 18.410 plan surface

Waste:

  • mq. 50.977 of asbestos/mineral wool on pipes
  • mq. 13.572 of asbestos/mineral wool on the ground
  • mq. 42.704 of polythene
  • 2.000 tons of reinforced concrete
  • 9.000 tons of ferrous scrap

 

ilva 1

Data

Customer: ILVA

Construction site: Centrale CET 1

Area: Taranto

Work Termination: 2010

 

 

Description of the job

Asbestos decontamination of the Descartes tower in Paris

139 metre-high Descartes tower is the 23rd highest building in Paris; but, in terms of surface covered, it is one of the largest buildings of the city. It was built in 1988 and hosted the IBM headquarters for years. It is currently 66% owned by Icade company, which decided to refurbish it.

The remediation works started in May 2010 and are scheduled to finish by September 2011.

The remediation intervention covers 41 floors; because of the scope of these works and the short time available, a group of 3 companies, including TIA, was entrusted with this task. The asbestos used to be widely present as fire protection on walls, ceilings and beams and it has to be fully removed in complete safety.

These labour-intensive works require a high level of organisation within the worksite.

 

tour descartes

Data

Customer: Icade

Area: Parigi

Construction site: Tour Descartes

Year of completition: 2011

 

 

Description of the job

  • Characterisation Plan of the site
  • Final remediation project

This area is included in the National Plan of Contaminated Sites, as asbestos-polluted topsoil, soil and subsoil. Upon approval by the Ministry of the Environment and Territory, we carried out 54 corings and over 400 analyses to find asbestos and other pollutants - metals in particular - in different soil layers. After Arpa approved the results we obtained, the final remediation plan was drawn up.

Technical data

  • Size of the area: 100.000 m2
  • Amount of the contract: 450.000 €

 

fibronit

Data

Customer: Immobiliare Beta

Area: Bari

Construction site: Area ex Fibronit

Work Termination: 2005

 

 

Page 8 of 45

OUR HISTORY

The TIA group was founded after the war and became the leading asbestos removal company in Italy in the 1990s.

Read more

CONTACT US

Address: via Salomone 73, 20138 Milano (IT)
Phone number: +39 02 50 99 40 1
E-mail address: This email address is being protected from spambots. You need JavaScript enabled to view it.

Location

Top
Con la presente informativa sul trattamento dei dati personali desideriamo informarla circa le modalità e le finalità di trattamento dei dati personali raccolti durante la navigazione sul sito web www.tia.it, in conformità a quanto previsto Regolamento generale europeo (UE) sulla protezione dei dati Personali (Regolamento UE 2016/679).

Per leggere l'Informativa completa, cliccare qui.

Per leggere l'informativa sui cookies, cliccare qui.